EnglishItaliano
Home

Safety Targets

Scope Description
Simpledo Compliance Management, preventive and corrective actions
June 2012
Training Review of training plan
December 2011
BBS 50% reduction of injuries in departments with BBS applied
June 2012
Training/Informing personnel involved
December 2012
Application of system
June 2013
Examination of results
December 2013
Noise Scrutiny of the efficacy of the older PPEs
December 2013
Works at height Implementation of lifelines in Cartiere del Garda (Autostore and Transformer Cabinet)
December 2012
Manual handling Implementation of dedicated training plan for tasks exposed to specific risks
December 2013
Mechanised handling Feasibility study for the creation of a protective walkway for pedestrian access to the canteen
December 2012
Sample speed control of reel transport shuttle truck using tachograph
December 2012
Confined spaces Implementation of dedicated training plan for tasks exposed to specific risks
December 2013
Electricity hazard Alteration of the opening of medium voltage electrical control panels (A3, A10) to enable thermography without access to the adjacent zone
August 2012
In the event of a power supply to cabinet A2 from A1, provision to prevent PCC 6kV supply in A2 with two MV/MV transformers in parallel (excluding temporary manoeuvres or emergency)
Settembre 2012
Verification and updating of the calibration tables of the medium voltage protection, according to the new configurations required with the connection to Alto Garda Power
December 2012
Implementation of a more effective coupling system for key couplings
December 2011
Periodic verification of the correct operation of the alarm notification system from the isolation control panels; restoration of the signalling to the guarded location
December 2012
Prompt verification of the calibration of the PCC switches for the 2nd earth trip
December 2012
Verification of the reference/notification systems of earth failure of the circuits supplied by UPS
August 2013
Chemical hazard Incremental installation of emergency showers and eyewash stations
Novembre 2010
Update of Simpledo software in line with new regulations for chemical substances and compounds
June 2012
Asbestos Removal of asbestos remaining on-site(see environmental improvement 38)
2020
ATEX hazard Creation of ATEX alarm management procedure in coatings section
June 2012
Artificial optical radiation Analysis and implementation of corrective measures
June 2012